Al Jouf Agricultural unveils SAR 398.5m bids for electrification project

Riyadh — Mubasher: Al Jouf Agricultural Development Company’s board of directors approved bids totaling SAR 398.43 million for a major electrification project at its Busita facilities.

The project, part of the national liquid fuel displacement program, follows an initial board resolution on 28 January, which had set an estimated budget of SAR 500 million.

The approved scope of work includes the construction of internal electrical networks, external power connection cable lines, and engineering supervision and contract management for both internal and external works.

The company stated that the total value of SAR 398.43 million excludes value-added tax.

Execution is scheduled to begin before the end of the fourth quarter (Q4) of 2026, with a project duration of 13 months from the commencement date.

Al Jouf Agricultural is currently evaluating and negotiating the final phase of the project. The company expects to announce the financial impact upon completion and will disclose further developments as they occur.

At the end of September 2026, the company posted 71.27% lower net profits at SAR 20.97 million, compared to SAR 73.01 million in 9M-25.

Mubasher Contribution Time: 17-Nov-2026 07:03 (GMT)